Phase II Update – 9/24/2021

Project Schedule Update Early Site Work is Complete Building Contractor Mobilized Site Survey and Staking Footings/Foundation Begin week of 9/20/21 Substantial Completion Estimate: Winter 2022 Outstanding Submittals & RFI’s The following RFI’s are Outstanding: Roof Sheathing Storm Shelter Louvers Aluminum Feeders Critical Submittals: Tilt Concrete Shops Plumbing Valves Domestic Water Piping Specialties Storm Drainage Piping […]

Read More Phase II Update – 9/24/2021

McGrath Sitework Update

This summer, crews have been hard at work preparing the McGrath site for the new McGrath/BECC building. While it may not have looked very exciting so far, things are about to get a lot more interesting! From the outside, you’ve mostly seen what just looks like dirt being moved around. But if you take a […]

Read More McGrath Sitework Update

August 31st Community Update

On August 31st, we will host a Facilities and Construction Update for our community. The event will be livestreamed to our YouTube channel at bit.ly/bsdyoutube at 6:00 PM. Representatives from the architect team (HTK), the owner’s representative (Navigate), and the district will be on hand to provide updates and answer questions. We hope you will […]

Read More August 31st Community Update

ICS Named McGrath Contractor

During the July 20th, 2021 Board of Education meeting, the Brentwood School Board unanimously approved ICS as the construction contractor for the new McGrath building. ICS was recommended after a thorough vetting and interview process conducted by District personnel, Board Members, and the school district’s owner’s representative, Navigate Building Solutions. “ICS has shown a commitment […]

Read More ICS Named McGrath Contractor

Prop E Renderings

Since the passing of Proposition E in June 2020, the district and its Elementary Facilities Design Committee has worked with stakeholders throughout the community to design and plan a McGrath/BECC campus that will serve the needs of students, families, staff, and the community for generations to come. The following images are conceptual renderings that give […]

Read More Prop E Renderings

Prop E Logistics Planning

Early sitework is scheduled to begin at the McGrath campus at the end of May. As the community will begin seeing work start to take place in the neighborhood for the new BECC/McGrath construction, please review the following materials that will help explain the site logistics and planning. Prop E (Elementary & Early childhood) Timeline […]

Read More Prop E Logistics Planning

Prop E – Upcoming Dates

Over the past several weeks, the Brentwood community has had opportunities to participate in events and provide feedback about the Elementary/Early Childhood facilities process. Here are some upcoming dates with opportunities to learn more: April 29, 2021 – Design Committee Meeting May 18, 2021 – Board of Education Presentation To review background information, presentations, an FAQ, […]

Read More Prop E – Upcoming Dates

Prop E (Phase II) Upcoming Events

Be sure to check out the last post to read the latest update and watch the latest video about Prop E (Phase II) facilities and upcoming events. Next week, early childhood and elementary families and staff will have the opportunity to attend a Virtual Open House for their home school about the Phase II process […]

Read More Prop E (Phase II) Upcoming Events