Prop E Timeline

Phase 1: McGrath/BECC 6-Month Design Work Completed: 6/9/2021 Early Sitework Package Bidding: April 2021 Project Bidding: June/July 2021 Construction Completed: January 2023 Phase 2: Mark Twain Elementary Concept Design: January – March 2021 Design Hold: April – July 2021  (May push this design hold until September to see progress on McGrath as it will not […]

Read More Prop E Timeline

Update – 2/26/21

Elevator 2 – The lobby roof was installed this week with metal flashings and gutters coming next. Disconnect switch ship date still 3/3/21. Targeting completion in April. Elevator 3 – Proceeding with foundation underpinning with expected completion by the end of this week. Next week will see the start of foundations for the elevator pit. Building B Update: In the new lobby expansion, windows have been going […]

Read More Update – 2/26/21

Update – 2/19/2021

A Building Class is in session Gym is open for classes Cafeteria Fully Operational Auditorium Construction complete. BSD currently recoating floors under seating prior to opening space end of February. B Building Building Addition Lobby and Offices – Early April Main Addition – Early April Exterior Curtainwall System Started 2/8/21 Interior walls framed and MEPFP […]

Read More Update – 2/19/2021

Update – 2/8/2021

Elevator 2 – We are still tracking electrical switch ship date of 2/10/21. Completion is expected mid-March Elevator 3 – A recently discovered manhole and storm line are creating conflicts with Elevator 3, preventing foundation work from continuing. The manhole and storm line were covered by asphalt and did not appear on any drawings. The […]

Read More Update – 2/8/2021

Update – 1/20/2021

A Building Class is in session Gym is open for classes Auditorium complete. Ittner to perform Punchlist this week. “Pop Up” area roof completed. Existing RTU remained in place Structural steel completed Finishes will be with the B addition B BUILDING Building Addition Lobby and Offices – March 31 Corridor turned over to BSD January […]

Read More Update – 1/20/2021

Update – 1/8/2021

Over winter break, the construction team completed a majority of punch list items throughout the building. Sitework where construction trailers were located is being cleaned, having fences removed, and fresh sod laid down. New sidewalk has been poured and will be ready to use next week. Elevator work is continuing for the two new elevators. […]

Read More Update – 1/8/2021

Project Timeline Update

A Building Class is in session Gym is open for classes Auditorium stage curtains installing this week. Turnover to BSD over the holiday break. “Pop Up” area mason finished walls. Structural steel set. Roofing expected 12/21. Remaining punch list items expected to be completed over the holiday break. B BUILDING Building Addition Lobby and Offices […]

Read More Project Timeline Update

Update – 12/11/2020

This week, work is continuing throughout the building as well as the exterior of the campus where cleanup of the site location is underway. In Building A, the auditorium is nearing completion with the stage curtain installation and remaining floor cleanup taking place in the coming week. In Building B, progress is being made in […]

Read More Update – 12/11/2020

Update – 11/19/2020

A Building Class is in session Gym is open for classes Auditorium lighting and carpeting being installed. To be completed 11/24. “Pop Up” area demolition underway. Mason starting walls 11/20. B Building Building Addition Lobby and Offices – March 3 Corridor turned over to BSD December 11 Main Addition – January 15 3rd Floor – […]

Read More Update – 11/19/2020