Prop B Update – 7/29/2021

Elevators Elevator 2 (August 2021): K&S addressing all issues from failed inspection to be complete this week, re-inspection next week. Elevator 3 (September 2021): Camera/Jet of the 8” completed. Elevator Lobbies demo taking place in Bldg C. Steel roof decking being installed with roofing to follow next week. Schindler electrical following roof dry in. Building […]

Read More Prop B Update – 7/29/2021

ICS Named McGrath Contractor

During the July 20th, 2021 Board of Education meeting, the Brentwood School Board unanimously approved ICS as the construction contractor for the new McGrath building. ICS was recommended after a thorough vetting and interview process conducted by District personnel, Board Members, and the school district’s owner’s representative, Navigate Building Solutions. “ICS has shown a commitment […]

Read More ICS Named McGrath Contractor

Prop B Update – 7/8/2021

Elevators Elevator 2 (June 2021) Schindler is on site to complete their scope this week. Final inspection scheduled for next week, day/time TBD. Elevator 3 (July/August 2021)  Utility contractor to start today with area drains. Camera/Jet of the 8” to be scheduled next week. Grading contractor bringing area to rough grade. Building B Update Lobby […]

Read More Prop B Update – 7/8/2021

Prop B Update – 7/1/2021

Elevators Elevator 2 (June 2021) – Schindler to be scheduled for final connection and inspection. K&S to advise. Elevator 3 (July/August 2021)  – Masonry work completed. – Grading contractor bringing area to rough grade. Building B Update Lobby Expansion and Admin Offices (June 2021) Color Art working on options for Principals office furniture Friday 7/2/21.  […]

Read More Prop B Update – 7/1/2021

Prop B Update – 6/17/2021

Elevators Elevator 2 (June 2021) – Floor transitions, paint front, schedule Schindler for final inspection TBD. Elevator 3 (July/August 2021)  – Masonry work started this week. Building B Update Lobby Expansion and Admin Offices (June 2021) Punch week happening this week Color Art End of June Lower Level Meeting/Staff Rooms (April 2021) Color Art furniture […]

Read More Prop B Update – 6/17/2021

Prop B Update – 6/10/2021

ELEVATORS Elevator 2 (June 2021) Floor transitions, paint front, schedule Schindler for final inspection TBD. Elevator 3 (July/August 2021)  Masonry work started this week. Building B Update Lobby Expansion and Admin Offices (June 2021) Punch week of 6/14/21 Lower Level Meeting/Staff Rooms (April 2021) Furniture next couple weeks Multipurpose (August 2021) Painting this week. Building […]

Read More Prop B Update – 6/10/2021

Prop E Renderings

Since the passing of Proposition E in June 2020, the district and its Elementary Facilities Design Committee has worked with stakeholders throughout the community to design and plan a McGrath/BECC campus that will serve the needs of students, families, staff, and the community for generations to come. The following images are conceptual renderings that give […]

Read More Prop E Renderings

Prop B Timeline (Summer 2021)

With a majority of the project completed, the final areas of the Middle/High School construction project are scheduled to be finalized during Summer 2021. The areas listed below are what remains of the project to be completed. Anything not listed here has been turned over to the district and is in use or in the […]

Read More Prop B Timeline (Summer 2021)

Prop E Logistics Planning

Early sitework is scheduled to begin at the McGrath campus at the end of May. As the community will begin seeing work start to take place in the neighborhood for the new BECC/McGrath construction, please review the following materials that will help explain the site logistics and planning. Prop E (Elementary & Early childhood) Timeline […]

Read More Prop E Logistics Planning

Prop B Update – 5/19/2021

At the May 18, 2021 Board of Education Meeting, Navigate Building Solutions presented the latest timeline information for the Middle and High School project. To view the entire presentation, view the meeting archive on the district YouTube channel at bit.ly/bsdyoutube. B Building Update Lobby Addition (End of May Completion) Main Building Addition Level 2 (End […]

Read More Prop B Update – 5/19/2021