Truss delivery – 3/15/22

On March 15, 2022, we are expecting delivery of trusses for the construction site around midday. This delivery will require an 82 foot truck to enter via High School Drive and Manchester Road. The delivery company has worked with St. Louis County for all relevant permits, but we wanted to let you know about this […]

Advertisement

Read More Truss delivery – 3/15/22

PHASE II UPdate February 2022

Project Schedule Update February Updates Slab Poured Area C MEPFP Rough-Ins Masonry Block Areas A & C Steel Erection Exterior Wall Framing and Sheathing Areas A/B  Roof Truss Installation Area A Site Utilities Substantial Completion Estimate: Winter 2022 The following RFI’s are Outstanding: Plumbing Clarifications Lugs at Panel H1S Cleanouts Area B 2nd Floor AV Supply […]

Read More PHASE II UPdate February 2022

Phase II Update January 2022

Project Schedule Update January Updates Slab Prep – Area C MEPFP Rough Ins Masonry Block Areas A & B Steel Framework Exterior Wall Framing – Areas A & B Roof Truss Installation – Area A Site Utilities Substantial Completion Estimate: Winter 2022 The following RFI’s are Outstanding: CMU at Column Line 15 Hallway CMU at […]

Read More Phase II Update January 2022

Playground Renderings

Check out the latest renderings of the McGrath Elementary Playground! This new, future ready playground will be open to our students during the day and to the community when school is not in session! One of the best features of the playground design is accessible equipment that will allow any student the chance to participate […]

Read More Playground Renderings

Phase II Update – December 2021

Project Schedule Update December Updates Slab Pours at Areas A & B Plumbing and Electrical Wall Rough-ins Masonry Block Areas A & B Site Utility Work Continues Tilt Panel Construction & Pours Substantial Completion Estimate: Winter 2022 Outstanding Submittals/RFIs The following RFI’s are Outstanding: Steel Blockouts/Waterproofing Fire Rating at Door 190 Steel Deck Attachment Info […]

Read More Phase II Update – December 2021

PHASE I (PROP B) Final Summary

Phase I of the Brentwood School District facilities updates was substantially completed on August 23, 2021, with final completion of elevator 3 and minor punch and warranty items completed throughout winter 2021.  Below is a summary of the final costs associated with the project.  Original Budget Final Costs Construction Costs $18,496,000 $20,458,823 Special Construction $0 […]

Read More PHASE I (PROP B) Final Summary

Phase II Update November 2021

Project Schedule Update November Updates Slab Pours Plumbing and Electrical Underground Rough-ins Masonry Block Started Site Utilities Started Tilt Panel Construction Started Substantial Completion Estimate: Winter 2022 Outstanding Submittals/RFPs The following RFI’s are Outstanding: Tilt Electrical Rough-ins Critical Submittals: TPO Roofing Asphalt Shingle PD CMU Samples Ceramic Tile Wood Flooring Glass and Glazing Food Service […]

Read More Phase II Update November 2021

Phase II Update October 2021

Project Schedule Update Early Site Work is Complete Building Contractor Mobilized Site Survey and Staking Footings/Foundation work has begun Plumbing and electrical rough-ins underway Masonry brick wall to start on elevator shaft Substantial Completion Estimate: Winter 2022 Outstanding Submittals & RFI’s The following RFI’s are Outstanding: Expansion Joint Locations Anchor Bolt Emergency Fixtures at Shelter […]

Read More Phase II Update October 2021

Phase II Update September 2021

Project Schedule Update Early Site Work is Complete Building Contractor Mobilized Site Survey and Staking Footings/Foundation Begin week of 9/20/21 Substantial Completion Estimate: Winter 2022 Outstanding Submittals & RFI’s The following RFI’s are Outstanding: Roof Sheathing Storm Shelter Louvers Aluminum Feeders Critical Submittals: Tilt Concrete Shops Plumbing Valves Domestic Water Piping Specialties Storm Drainage Piping […]

Read More Phase II Update September 2021