Truss delivery – 3/15/22

On March 15, 2022, we are expecting delivery of trusses for the construction site around midday. This delivery will require an 82 foot truck to enter via High School Drive and Manchester Road. The delivery company has worked with St. Louis County for all relevant permits, but we wanted to let you know about this […]

Read More Truss delivery – 3/15/22

PHASE II UPdate February 2022

Project Schedule Update February Updates Slab Poured Area C MEPFP Rough-Ins Masonry Block Areas A & C Steel Erection Exterior Wall Framing and Sheathing Areas A/B  Roof Truss Installation Area A Site Utilities Substantial Completion Estimate: Winter 2022 The following RFI’s are Outstanding: Plumbing Clarifications Lugs at Panel H1S Cleanouts Area B 2nd Floor AV Supply […]

Read More PHASE II UPdate February 2022