Prop B Update – 5/7/2021

Elevators Elevator 2 (May 2021): Drywall returns framed an drywalled this week. Schindler electric to schedule inspection in the coming weeks. Elevator 3 (July 2021): Masonry infill window and waterproofing taking place this week. Backfill and retaining wall demo to happen next. Building B Update Lobby Expansion (May 2021) Flooring installation underway. Aluminum storefront and […]

Read More Prop B Update – 5/7/2021

Prop B Update – 4/30/2021

Elevators Elevator 2 (May 2021) JDS to complete masonry returns today, drywall complete with MEPFP next week. Elevator 3 (July 2021)  Masonry today, waterproofing next week and demo of retaining wall and backfill to follow. Building B Update Lobby Expansion (May 2021) MEPFP Trim started this week. Lower Level Meeting/Staff Rooms (April 2021) Downspout and […]

Read More Prop B Update – 4/30/2021

Prop B Update – 4/23/2021

Elevators Elevator 2 (May 2021) Schindler installation is complete. Punch/completion items by K&S to take 1-2 weeks, then Schindler will return to make final electrical connection and inspections. Elevator 3 (July 2021) Foundations are complete. Waterproofing walls this week, backfill and masonry to be next week. Building B Update Lobby Expansion (May 2021) Painting started […]

Read More Prop B Update – 4/23/2021

Prop B Update – 4/16/2021

Elevators Elevator 2 (April 2021) Schindler to complete work today. Charter line is complete. Punch work will take place for 1-2 weeks followed by Final State Inspection. Elevator 3 (July 2021)  Foundation pours taking place this week with slab pours next week. Building B Update Lobby Expansion (May 2021) Drywall taping ongoing currently. Painting taking […]

Read More Prop B Update – 4/16/2021

Prop B Update – 4/2/2021

Over Spring Break, construction crews worked on areas of the building normally occupied by students and staff, primarily tackling warranty and punch-list work such as tackboards, LVT flooring, and painting. Elevator 2 (April 2021) Schindler started this week. Charter line install is taking place today. On schedule for mid-late April for completion. Elevator 3 (July […]

Read More Prop B Update – 4/2/2021

Prop B Update – 3/12/2021

Elevator Updates Elevator 2 – Disconnect switch installation began this week. Schindler (elevator contractor) was on site for a pre-install walk this week. Schindler expects a start date of 3/31, with final completion still looking like the end of April. Elevator 3 – Foundation underpinning completed 3/2/21. Direction was given to encase 8” storm drain […]

Read More Prop B Update – 3/12/2021

Update – 2/26/21

Elevator 2 – The lobby roof was installed this week with metal flashings and gutters coming next. Disconnect switch ship date still 3/3/21. Targeting completion in April. Elevator 3 – Proceeding with foundation underpinning with expected completion by the end of this week. Next week will see the start of foundations for the elevator pit. Building B Update: In the new lobby expansion, windows have been going […]

Read More Update – 2/26/21

Update – 2/19/2021

A Building Class is in session Gym is open for classes Cafeteria Fully Operational Auditorium Construction complete. BSD currently recoating floors under seating prior to opening space end of February. B Building Building Addition Lobby and Offices – Early April Main Addition – Early April Exterior Curtainwall System Started 2/8/21 Interior walls framed and MEPFP […]

Read More Update – 2/19/2021

Update – 2/8/2021

Elevator 2 – We are still tracking electrical switch ship date of 2/10/21. Completion is expected mid-March Elevator 3 – A recently discovered manhole and storm line are creating conflicts with Elevator 3, preventing foundation work from continuing. The manhole and storm line were covered by asphalt and did not appear on any drawings. The […]

Read More Update – 2/8/2021

Update – 1/20/2021

A Building Class is in session Gym is open for classes Auditorium complete. Ittner to perform Punchlist this week. “Pop Up” area roof completed. Existing RTU remained in place Structural steel completed Finishes will be with the B addition B BUILDING Building Addition Lobby and Offices – March 31 Corridor turned over to BSD January […]

Read More Update – 1/20/2021