Project Schedule Update
January Updates
- Slab Prep – Area C
- MEPFP Rough Ins
- Masonry Block Areas A & B
- Steel Framework
- Exterior Wall Framing – Areas A & B
- Roof Truss Installation – Area A
- Site Utilities
Substantial Completion Estimate: Winter 2022
The following RFI’s are Outstanding:
- CMU at Column Line 15
- Hallway CMU at Multipurpose
- Access Control at Pedestal
- CMU Columns at Gymnasium
- Fire Rating at Door 190
Critical Submittals:
- Intercom Submittals
- Roofing Submittals
- Sheet Metal Submittals
- Flooring Submittals
- Food Service Equipment
Schedule Risks
- Unforeseen Conditions
- Potential Material Delivery Delays
- Weather
- Potential Labor Shortage
Budget Risks
- Unforeseen Conditions
Contingency Budget
Original Contingency: $755,200
Contingency Spent: $33,168
Anticipated Changes: $116,200
Anticipated Contingency Remaining: $605,832
*Anticipated changes are being tracked and discussed in bi-weekly OAC meetings.
Unknown Conditions Allowance
Original Allowance: $100,000
Remaining Allowance: $92,000
Construction Contract
Original Contract: $15,104,000
Changes to Date: $33,168
Current Contract: $15,137,168



