Project Timeline Update

A Building Class is in session Gym is open for classes Auditorium stage curtains installing this week. Turnover to BSD over the holiday break. “Pop Up” area mason finished walls. Structural steel set. Roofing expected 12/21. Remaining punch list items expected to be completed over the holiday break. B BUILDING Building Addition Lobby and Offices […]

Read More Project Timeline Update

Update – 12/11/2020

This week, work is continuing throughout the building as well as the exterior of the campus where cleanup of the site location is underway. In Building A, the auditorium is nearing completion with the stage curtain installation and remaining floor cleanup taking place in the coming week. In Building B, progress is being made in […]