Update – 2/26/21
Elevator 2 – The lobby roof was installed this week with metal flashings and gutters coming next. Disconnect switch ship date still 3/3/21. Targeting completion in April. Elevator 3 – Proceeding with foundation underpinning with expected completion by the end of this week. Next week will see the start of foundations for the elevator pit. Building B Update: In the new lobby expansion, windows have been going […]
Read More Update – 2/26/21