Phase II Update January 2022
Project Schedule Update January Updates Slab Prep – Area C MEPFP Rough Ins Masonry Block Areas A & B Steel Framework Exterior Wall Framing – Areas A & B Roof Truss Installation – Area A Site Utilities Substantial Completion Estimate: Winter 2022 The following RFI’s are Outstanding: CMU at Column Line 15 Hallway CMU at […]
Read More Phase II Update January 2022