Prop B Update – 6/17/2021

Elevators Elevator 2 (June 2021) – Floor transitions, paint front, schedule Schindler for final inspection TBD. Elevator 3 (July/August 2021)  – Masonry work started this week. Building B Update Lobby Expansion and Admin Offices (June 2021) Punch week happening this week Color Art End of June Lower Level Meeting/Staff Rooms (April 2021) Color Art furniture […]

Read More Prop B Update – 6/17/2021

Prop B Update – 6/10/2021

ELEVATORS Elevator 2 (June 2021) Floor transitions, paint front, schedule Schindler for final inspection TBD. Elevator 3 (July/August 2021)  Masonry work started this week. Building B Update Lobby Expansion and Admin Offices (June 2021) Punch week of 6/14/21 Lower Level Meeting/Staff Rooms (April 2021) Furniture next couple weeks Multipurpose (August 2021) Painting this week. Building […]

Read More Prop B Update – 6/10/2021