Phase II Update October 2021

Project Schedule Update Early Site Work is Complete Building Contractor Mobilized Site Survey and Staking Footings/Foundation work has begun Plumbing and electrical rough-ins underway Masonry brick wall to start on elevator shaft Substantial Completion Estimate: Winter 2022 Outstanding Submittals & RFI’s The following RFI’s are Outstanding: Expansion Joint Locations Anchor Bolt Emergency Fixtures at Shelter […]