Prop E Timeline

Timeline Overview

Phase 1: McGrath/BECC

  • Early Sitework Package Bidding: April/May 2021
  • Project Bidding: May/June 2021
  • Construction Completed: December 2022
  • Fall 2023 – McGrath students attend school in new building; Mark Twain students begin their year at the old McGrath building

Phase 2: Mark Twain Elementary

  • Design Hold: June-September 2021
  • Concept Design: October-December 2021
  • Complete Design: March 2022
  • Fall 2023: Mark Twain students begin their year at the old McGrath building
  • Construction Completed: June 2024