Update – 11/19/2020
A Building Class is in session Gym is open for classes Auditorium lighting and carpeting being installed. To be completed 11/24. “Pop Up” area demolition underway. Mason starting walls 11/20. B Building Building Addition Lobby and Offices – March 3 Corridor turned over to BSD December 11 Main Addition – January 15 3rd Floor – […]
Read More Update – 11/19/2020