Project Schedule Update
November Updates
- Slab Pours
- Plumbing and Electrical Underground Rough-ins
- Masonry Block Started
- Site Utilities Started
- Tilt Panel Construction Started
Substantial Completion Estimate: Winter 2022
Outstanding Submittals/RFPs
The following RFI’s are Outstanding:
- Tilt Electrical Rough-ins
Critical Submittals:
- TPO Roofing
- Asphalt Shingle PD
- CMU Samples
- Ceramic Tile
- Wood Flooring
- Glass and Glazing
- Food Service Equipment
- Air Terminals
Owner Hot List
Schedule Risks
- Unforeseen Conditions
- Potential Material Delivery Delays
- Weather
- Potential Labor Shortage
Budget Risks
- Unforeseen Conditions
Contingency/Allowances
Contingency Budget
Original Contingency: $755,200
Contingency Spent: $33,168
Anticipated Changes: $20,000
Anticipated Contingency Remaining: $702,032
*Anticipated changes are being tracked and discussed in bi-weekly OAC meetings.
Unknown Conditions Allowance
Original Allowance: $100,000
Remaining Allowance: $100,000
Construction Contract
Original Contract: $15,104,000
Changes to Date: $33,168
Current Contract: $15,137,168