Project Schedule Update
February Updates
- Slab Poured Area C
- MEPFP Rough-Ins
- Masonry Block Areas A & C
- Steel Erection
- Exterior Wall Framing and Sheathing Areas A/B
- Roof Truss Installation Area A
- Site Utilities
Substantial Completion Estimate: Winter 2022
The following RFI’s are Outstanding:
- Plumbing Clarifications
- Lugs at Panel H1S
- Cleanouts Area B 2nd Floor
- AV Supply Chain Substitution
Critical Submittals:
- Roofing Submittals
- Glazing Submittals
- Flooring Submittals
- Food Service Equipment
- Roller Shad Submittals
- Ductwork Submittals
Schedule Risks
- Unforeseen Conditions
- Potential Material Delivery Delays
- Weather
- Potential Labor Shortage
Budget Risks
- Unforeseen Conditions
Contingency Budget
Original Contingency: $755,200
Contingency Spent: $68,234
Anticipated Changes: $77,852
Anticipated Contingency Remaining: $609,114
*Anticipated changes are being tracked and discussed in bi-weekly OAC meetings.
Unknown Conditions Allowance
Original Allowance: $100,000
Remaining Allowance: $91,133
Construction Contract
McGrath Early Site Work (Completed Work)
L. Keeley Construction Original Contract: $1,228,264
Total CO’s (x2): ($14,043)
Current Contract: $1,214,221
Projected Contract: $1,214,221
Total Projected Savings Against Bond: $14,043
McGrath Building (Work In Progress)
ICS Construction Original Contract: $15,104,000
Changes to Date: $68,234 (*thru CO #2) Current Contract: $15,172,234
Projected Spent Contingency: $200,000
Projected Contract: $15,372,234
Total Projected Savings Against Bond: $500,000


