Phase II Update – December 2021

Project Schedule Update

December Updates

  • Slab Pours at Areas A & B
  • Plumbing and Electrical Wall Rough-ins
  • Masonry Block Areas A & B
  • Site Utility Work Continues
  • Tilt Panel Construction & Pours

Substantial Completion Estimate: Winter 2022

Outstanding Submittals/RFIs

The following RFI’s are Outstanding:

  • Steel Blockouts/Waterproofing
  • Fire Rating at Door 190
  • Steel Deck Attachment Info

Critical Submittals:

  • Fire Alarm System
  • Video Surveillance System
  • Access Control System
  • Intercom & Paging Systems
  • Overcurrent Device Study
  • Food Service Equipment

Owner Hot List

Schedule Risks

  • Unforeseen Conditions
  • Potential Material Delivery Delays
  • Weather
  • Potential Labor Shortage

Budget Risks

  • Unforeseen Conditions
  • Flooring Submittals
  • Curtainwall Submittals
  • Roofing Submittals

Contingency Budget

Original Contingency:  $755,200 

Contingency Spent: $33,168

Anticipated Changes: $66,712

Anticipated Contingency Remaining:   $655,320

*Anticipated changes are being tracked and discussed in bi-weekly OAC meetings.

Unknown Conditions Allowance

Original Allowance: $100,000

Remaining Allowance: $95,000

Construction Contract

Original Contract: $15,104,000

Changes to Date: $33,168

Current Contract: $15,137,168

Advertisement

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s