Project Schedule Update
December Updates
- Slab Pours at Areas A & B
- Plumbing and Electrical Wall Rough-ins
- Masonry Block Areas A & B
- Site Utility Work Continues
- Tilt Panel Construction & Pours
Substantial Completion Estimate: Winter 2022
Outstanding Submittals/RFIs
The following RFI’s are Outstanding:
- Steel Blockouts/Waterproofing
- Fire Rating at Door 190
- Steel Deck Attachment Info
Critical Submittals:
- Fire Alarm System
- Video Surveillance System
- Access Control System
- Intercom & Paging Systems
- Overcurrent Device Study
- Food Service Equipment
Owner Hot List
Schedule Risks
- Unforeseen Conditions
- Potential Material Delivery Delays
- Weather
- Potential Labor Shortage
Budget Risks
- Unforeseen Conditions
- Flooring Submittals
- Curtainwall Submittals
- Roofing Submittals
Contingency Budget
Original Contingency: $755,200
Contingency Spent: $33,168
Anticipated Changes: $66,712
Anticipated Contingency Remaining: $655,320
*Anticipated changes are being tracked and discussed in bi-weekly OAC meetings.
Unknown Conditions Allowance
Original Allowance: $100,000
Remaining Allowance: $95,000
Construction Contract
Original Contract: $15,104,000
Changes to Date: $33,168
Current Contract: $15,137,168


