Project Schedule Update
- Early Site Work is Complete
- Building Contractor Mobilized
- Site Survey and Staking
- Footings/Foundation work has begun
- Plumbing and electrical rough-ins underway
- Masonry brick wall to start on elevator shaft
Substantial Completion Estimate: Winter 2022
Outstanding Submittals & RFI’s
The following RFI’s are Outstanding:
- Expansion Joint Locations
- Anchor Bolt
- Emergency Fixtures at Shelter
- Flagpole Submittal Comments
Critical Submittals:
- CMU Rebar Shops
- Cold-Formed Metal Trusses
- Doors/Fames/Hardware
Owner Hot List / Risks
Schedule Risks
- Unforeseen Conditions
- Potential Material Delivery Delays
- Weather
- Potential Labor Shortage
Budget Risks
- Unforeseen Conditions
Contingency / Allowances
Original Contingency: | $755, 200 |
Contingency Spent: | $0 |
Anticipated Changes: | $29,821 |
Anticipated Contingency Remaining: | $725,379 |
Unknown Conditions Allowance | |
Original Allowance | $100,000 |
Remaining Allowance | $100,000 |
McGrath/BECC Construction Contract
Original Contract: | $15,104,000 |
Changes to Date: | $0 |
Current Contract: | $15,104,000 |