Update – 1/20/2021

A Building Class is in session Gym is open for classes Auditorium complete. Ittner to perform Punchlist this week. “Pop Up” area roof completed. Existing RTU remained in place Structural steel completed Finishes will be with the B addition B BUILDING Building Addition Lobby and Offices – March 31 Corridor turned over to BSD January […]

Read More Update – 1/20/2021

Update – 1/8/2021

Over winter break, the construction team completed a majority of punch list items throughout the building. Sitework where construction trailers were located is being cleaned, having fences removed, and fresh sod laid down. New sidewalk has been poured and will be ready to use next week. Elevator work is continuing for the two new elevators. […]