Prop B Update – 3/12/2021
Elevator Updates Elevator 2 – Disconnect switch installation began this week. Schindler (elevator contractor) was on site for a pre-install walk this week. Schindler expects a start date of 3/31, with final completion still looking like the end of April. Elevator 3 – Foundation underpinning completed 3/2/21. Direction was given to encase 8” storm drain […]
Read More Prop B Update – 3/12/2021