Elevators
- Elevator 2 (August 2021): K&S addressing all issues from failed inspection to be complete this week, re-inspection next week.
- Elevator 3 (September 2021): Camera/Jet of the 8” completed.
- Elevator Lobbies demo taking place in Bldg C.
- Steel roof decking being installed with roofing to follow next week.
- Schindler electrical following roof dry in.
Building B
- Multipurpose Room (August 2021)
- Floor demo complete this week. New floor delivered this week, start installing next week.
- Health Room Floor installed this week.
Building B Expansion
- Lower Level (July 2021)
- K&S finishing up Bathrooms.
- Inverter in Weight Room this week.
- Level1 (July 2021)
- Commons to be punched 8/4/21
- Level2 (June 2021)
- Punch Corridor and Connectors Complete
Site Update (August 2021)
- Bommarito grading out North Side.
- “Upper” Parking Pavers will complete Monday the 2nd.
- North Drive Curbs today.
- Landscape/Irrigation to start 8/11/21.