Prop B Update – 7/29/2021

Elevators

  • Elevator 2 (August 2021): K&S addressing all issues from failed inspection to be complete this week, re-inspection next week.
  • Elevator 3 (September 2021): Camera/Jet of the 8” completed.
  • Elevator Lobbies demo taking place in Bldg C.
  • Steel roof decking being installed with roofing to follow next week.
  • Schindler electrical following roof dry in.

Building B

  • Multipurpose Room (August 2021)
    • Floor demo complete this week. New floor delivered this week, start installing next week.
  • Health Room Floor installed this week.

Building B Expansion

  • Lower Level (July 2021)
    • K&S finishing up Bathrooms.
    • Inverter in Weight Room this week.
  • Level1 (July 2021)
    • Commons to be punched 8/4/21
  • Level2 (June 2021)
    • Punch Corridor and Connectors Complete

Site Update (August 2021)

  • Bommarito grading out North Side.
  • “Upper” Parking Pavers will complete Monday the 2nd.
  • North Drive Curbs today.
  • Landscape/Irrigation to start 8/11/21.
Brentwood Middle School Office
Library

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s