Elevators
Elevator 2 (June 2021)
– Floor transitions, paint front, schedule Schindler for final inspection TBD.
Elevator 3 (July/August 2021)
– Masonry work started this week.
Building B Update
- Lobby Expansion and Admin Offices (June 2021)
- Punch week happening this week
- Color Art End of June
- Lower Level Meeting/Staff Rooms (April 2021)
- Color Art furniture possibly next week
- Multipurpose (August 2021)
- Painting continues.
Building B Expansion Update
- Lower Level (June 2021)
- Floor install start 6/21
- Level 1 (June 2021)
- MEPFP Trim Out.
- Column Wraps.
- Flooring Started this week.
- Level 2 (June 2021)
- Furniture Move-In Started
Site Update (July/August 2021)
- South Paver Area start pavers today!
- Pouring sidewalks and curbs throughout.
- Water/Gas Line discovered 6/7 at northwest side impacting west paver section. Gas line will be abandoned, and water will be lowered approximately 3.5’ to accommodate.