Elevators
Elevator 2 (June 2021)
– Schindler to be scheduled for final connection and inspection. K&S to advise.
Elevator 3 (July/August 2021)
– Masonry work completed.
– Grading contractor bringing area to rough grade.
Building B Update
- Lobby Expansion and Admin Offices (June 2021)
- Color Art working on options for Principals office furniture Friday 7/2/21.
- Multipurpose (August 2021)
- Flooring contractor started 6/30/21.
Building B Expansion Update
- Lower Level (July 2021)
- Rubber/Turf Floor completing this week.
- Punch Scheduled for 7/5
- Weight Equipment scheduled for 7/13
- Level 1 (July 2021)
- Reception Desk
- Flooring
- Casework/Counters
- Level 2 (June 2021)
- Library turned over.
Site Update (August 2021)
- South Paver Area pavers complete.
- Paver Parking Area being graded and under drain system installed.
- Curbing to continue Thursday.

