Prop B Update – 7/8/2021

Elevators

  • Elevator 2 (June 2021)
    • Schindler is on site to complete their scope this week. Final inspection scheduled for next week, day/time TBD.
  • Elevator 3 (July/August 2021) 
    • Utility contractor to start today with area drains.
    • Camera/Jet of the 8” to be scheduled next week.
    • Grading contractor bringing area to rough grade.

Building B Update

  • Lobby Expansion and Admin Offices (June 2021)
    • Color Art moving Principal Offices Friday the 9th.
  • Multipurpose (August 2021)
    • Floor demo complete this week. New floor should start going down next week.

Building B Expansion Update

  • Lower Level (July 2021)
    • Rubber patch complete today. Maintenance coat and turf before Tuesday.
    • Weight Equipment scheduled for 7/13.
    • Punch of LL – TBD
  • Level 1 (July 2021)
    • Reception Desk
    • Flooring
    • Casework/Counters
  • Level 2 (June 2021)
    • Library turned over.

Site Update (August 2021)

  • “Upper” Parking Pavers begin today.
  • Curbing and sidewalks to continue late this week.
View of interior courtyard from Library

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s