Elevators
- Elevator 2 (June 2021)
- Schindler is on site to complete their scope this week. Final inspection scheduled for next week, day/time TBD.
- Elevator 3 (July/August 2021)
- Utility contractor to start today with area drains.
- Camera/Jet of the 8” to be scheduled next week.
- Grading contractor bringing area to rough grade.
Building B Update
- Lobby Expansion and Admin Offices (June 2021)
- Color Art moving Principal Offices Friday the 9th.
- Multipurpose (August 2021)
- Floor demo complete this week. New floor should start going down next week.
Building B Expansion Update
- Lower Level (July 2021)
- Rubber patch complete today. Maintenance coat and turf before Tuesday.
- Weight Equipment scheduled for 7/13.
- Punch of LL – TBD
- Level 1 (July 2021)
- Reception Desk
- Flooring
- Casework/Counters
- Level 2 (June 2021)
- Library turned over.
Site Update (August 2021)
- “Upper” Parking Pavers begin today.
- Curbing and sidewalks to continue late this week.

