Prop B Update – 4/30/2021

Elevators Elevator 2 (May 2021) JDS to complete masonry returns today, drywall complete with MEPFP next week. Elevator 3 (July 2021)  Masonry today, waterproofing next week and demo of retaining wall and backfill to follow. Building B Update Lobby Expansion (May 2021) MEPFP Trim started this week. Lower Level Meeting/Staff Rooms (April 2021) Downspout and […]

Read More Prop B Update – 4/30/2021

Prop B Update – 4/2/2021

Over Spring Break, construction crews worked on areas of the building normally occupied by students and staff, primarily tackling warranty and punch-list work such as tackboards, LVT flooring, and painting. Elevator 2 (April 2021) Schindler started this week. Charter line install is taking place today. On schedule for mid-late April for completion. Elevator 3 (July […]

Read More Prop B Update – 4/2/2021

Update – 1/20/2021

A Building Class is in session Gym is open for classes Auditorium complete. Ittner to perform Punchlist this week. “Pop Up” area roof completed. Existing RTU remained in place Structural steel completed Finishes will be with the B addition B BUILDING Building Addition Lobby and Offices – March 31 Corridor turned over to BSD January […]

Read More Update – 1/20/2021

Update – 12/11/2020

This week, work is continuing throughout the building as well as the exterior of the campus where cleanup of the site location is underway. In Building A, the auditorium is nearing completion with the stage curtain installation and remaining floor cleanup taking place in the coming week. In Building B, progress is being made in […]

Read More Update – 12/11/2020

Update – 9/25/2020

Finishing touches for many classrooms are underway. As rooms are completed, the Brentwood Maintenance Department is doing final cleaning and movement of teacher materials. Some updates taking place now include: Tack boards for Art Room Temporary walkway to cafeteria to provide an additional route Sink tops in new restrooms Corridor outside of large gym is […]

Read More Update – 9/25/2020

Update – 9/8/2020

As we enter September, there have been several major updates to the completion of rooms in Building A. With the exception of some sinks and plumbing, there is substantial completion in this portion of the building. In Building B, priorities include the Nurse’s Station and Guidance Office. Upstairs rooms need flooring and ceiling grid to […]

Read More Update – 9/8/2020

K&S Construction Schedule Update

During the August 18, 2020 Board of Education meeting, the president of K&S Construction provided a schedule update for the remainder of the Middle/High School construction project. You can view the entire Board Meeting on our YouTube channel at bit.ly/bsdyoutube. Below is a copy of the revised schedule. A PDF of the schedule is available […]

Read More K&S Construction Schedule Update

June Recap

Construction is progressing for the middle and high school project, with classroom renovations taking place throughout the building. Due to COVID-19 and delays in ordering material, additional safety precautions for construction staff, and physical distancing needs, the construction timeline will likely extend into the Fall and the beginning of the school year. More details will […]

Read More June Recap

Elementary Facilities Volunteers

With the successful passage of Proposition E, we are turning our attention to the next phase of our elementary facilities planning work. We are seeking volunteers to apply to serve on the Elementary Facilities Planning Committee for the 2020-2021 school year.  The Elementary Facilities Planning Committee is composed of Brentwood School District Board of Education […]

Read More Elementary Facilities Volunteers