Prop B Update – 4/2/2021

Over Spring Break, construction crews worked on areas of the building normally occupied by students and staff, primarily tackling warranty and punch-list work such as tackboards, LVT flooring, and painting.

Elevator 2 (April 2021)

Schindler started this week. Charter line install is taking place today. On schedule for mid-late April for completion.

Elevator 3 (July 2021) 

Foundation slab and walls being formed and rebar placed.

Building B Update

  • Lobby Expansion (May 2021)
    • Ceiling framing and MEPFP rough-in taking place.
  • Lower Level Meeting/Staff Rooms (April 2021)
    • Floor leveling waiting for downspout work to be complete outside.
  • Level 1 Office/Admin Rooms (May 2021)
    • LVT2 Material for Admin area was delayed now until mid-late April, pushing this space into May.

Building B Expansion Update

  • Courtyard pavers being installed.
  • Lower Level (June 2021)
    • French drain work will be finished with “dirty work” this weekend. Electric and plumbing connections to follow for sumps. K&S can then complete finishes. 
  • Level 1 (June 2021)
    • continue with drywall and MEPFP
  • Level 2 (May 2021)
    • drywall taping to be complete next week. 
  • Pop-Up (May 2021)
    • connector with A Building is now drywalled.

Site Update (June 2021)

  • Retaining wall for ramp at south side of circle drive has begun this week.
Advertisement

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s