K&S Construction Schedule Update

During the August 18, 2020 Board of Education meeting, the president of K&S Construction provided a schedule update for the remainder of the Middle/High School construction project. You can view the entire Board Meeting on our YouTube channel at bit.ly/bsdyoutube.

Below is a copy of the revised schedule. A PDF of the schedule is available by clicking here.

First Floor

First Floor Diagram

Large Gymnasium – Complete

1st Floor Building C Classrooms – Complete

  • Language Arts
  • Flexible Learning Spaces
  • Testing Labs

Cafeteria – Complete

Auditorium – 11/15/2020

1st Floor Classrooms – 8/21/2020

  • Art
  • Math
  • Language Arts
  • Social Studies

New Commons and Entrance – 12/07/2020

Middle School Offices – 10/02/2020

Elevators – 11/27/2020

Access Ramp – 8/28/2020

1st Floor Storage and Staff Areas – 10/02/2020

  • Student Council Storage
  • Meeting Rooms
  • Mechanical Closets

Second Floor

2nd Floor Plan
Second Floor Diagram

Large Gymnasium – Complete

2nd Floor Building C Classrooms – Complete

  • Math
  • Social Studies
  • Lecture Hall

2nd Floor Classrooms – 08/21/2020

  • Math
  • Language Arts
  • Science

Staff Offices and Classrooms – 10/02/2020

  • Nurse’s Office
  • Staff Lounge
  • Reading

FACS and SSD Rooms – 10/02/2020

High School Offices – 11/16/2020

Small Gymnasium – 01/07/2021

Third Floor

3rd floor plan
Third Floor Diagram

3rd Floor Science Labs – Completed

  • Biology
  • Chemistry
  • Physics
  • Science Flex Lab

3rd Floor Classrooms – 10/02/2020

  • World Languages
  • Art
  • Math
  • Language Arts
  • Social Studies
  • Flexible Learning Space
Advertisement

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s