Update – 1/20/2021

A Building

  • Class is in session
  • Gym is open for classes
  • Auditorium complete. Ittner to perform Punchlist this week.
  • “Pop Up” area roof completed.
    • Existing RTU remained in place
    • Structural steel completed
    • Finishes will be with the B addition

B BUILDING

  • Building Addition
    • Lobby and Offices – March 31
      • Corridor turned over to BSD January 19 – lacking flooring
      • Concrete SOG poured
    • Main Addition – March 31
      • Mason completing west side 1/20
      • Interior walls framed and MEP roughing in
      • Drywall expected end of January
      • Temp windows being installed currently
      • Roofing completed
    • 3rd Floor – Turned over
    • 2nd floor – Turned over
    • 1st Floor
      • Rooms at bottom of main stairs – February
      • Chimney work completed.

C Building

Turned over to the District.

Elevators

  • #2 – B Building
    • Shaft Completed
    • Roofing completed
    • Door openings being demoed
    • Elevator company starting February
    • Expected completion March 1
  • #3 – B/C Building
    • Excavation completed
    • Existing undocumented storm uncovered. Planned developed to replace.
    • Expected completion May 1

Sitework

  • “A” Building
    • Sod weather completed
    • Sidewalk completed
    • Fencing removed
  • “B” Building
    • Site grading/utilities contactor expected completion late February – pending weather
    • ADA ramp demolished
    • Elevator 3 excavation complete
    • Manhole to be replaced
Advertisement

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s