A Building
- Class is in session
- Gym is open for classes
- Auditorium complete. Ittner to perform Punchlist this week.
- “Pop Up” area roof completed.
- Existing RTU remained in place
- Structural steel completed
- Finishes will be with the B addition
B BUILDING
- Building Addition
- Lobby and Offices – March 31
- Corridor turned over to BSD January 19 – lacking flooring
- Concrete SOG poured
- Main Addition – March 31
- Mason completing west side 1/20
- Interior walls framed and MEP roughing in
- Drywall expected end of January
- Temp windows being installed currently
- Roofing completed
- 3rd Floor – Turned over
- 2nd floor – Turned over
- 1st Floor
- Rooms at bottom of main stairs – February
- Chimney work completed.
- Lobby and Offices – March 31
C Building
Turned over to the District.

Elevators
- #2 – B Building
- Shaft Completed
- Roofing completed
- Door openings being demoed
- Elevator company starting February
- Expected completion March 1
- #3 – B/C Building
- Excavation completed
- Existing undocumented storm uncovered. Planned developed to replace.
- Expected completion May 1
Sitework
- “A” Building
- Sod weather completed
- Sidewalk completed
- Fencing removed
- “B” Building
- Site grading/utilities contactor expected completion late February – pending weather
- ADA ramp demolished
- Elevator 3 excavation complete
- Manhole to be replaced