Elevators
Elevator 2 (May 2021)
- JDS to complete masonry returns today, drywall complete with MEPFP next week.
Elevator 3 (July 2021)
- Masonry today, waterproofing next week and demo of retaining wall and backfill to follow.
Building B Update
- Lobby Expansion (May 2021)
- MEPFP Trim started this week.
- Lower Level Meeting/Staff Rooms (April 2021)
- Downspout and then floor leveling.
- Level 1 Office/Admin Rooms (May 2021)
- MEPFP trimming taking place.
- Storefront glass going in next week.
- LVT2 Material for Admin area was delayed, pushing this space into May.
- Multipurpose
- Library pack up week of May 17th w/ goal to be moved out by 5/24.
- Demo to start week of right after, no earlier than 5/27.
Building B Expansion Update
- Courtyard One opening to be bricked up.
- Lower Level (June 2021)
- Staat completed sump installation yesterday. Final electrical connections remain.
- Level 1 (June 2021)
- Drywall taping and MEPFP
- Level 2 (May 2021)
- Ceiling Grid started.
- Nano folding glass wall completed.
- MEPFP Trim Out.
- Pop-Up (May 2021)
- Above Ceiling MEPFP.
Site Update (June 2021)
- Site Coordination Meeting happened Tuesday of this week.
- Backfill for the switch-back ramp will take place after the next site coordination meeting.
- Ramp for lobby wall was poured and forms stripped.
Breezeway Doors
- Hardware ordered – Delivery/Install date pending from K&S