June Recap

Construction is progressing for the middle and high school project, with classroom renovations taking place throughout the building. Due to COVID-19 and delays in ordering material, additional safety precautions for construction staff, and physical distancing needs, the construction timeline will likely extend into the Fall and the beginning of the school year. More details will […]

Read More June Recap

Elementary Facilities Volunteers

With the successful passage of Proposition E, we are turning our attention to the next phase of our elementary facilities planning work. We are seeking volunteers to apply to serve on the Elementary Facilities Planning Committee for the 2020-2021 school year.  The Elementary Facilities Planning Committee is composed of Brentwood School District Board of Education […]

Read More Elementary Facilities Volunteers

April Recap

With the announcement that schools in Missouri will be closed for the remainder of the semester, construction crews for the Middle and High School project will be able to have greater access to the buildings than previously anticipated. Currently, school admin and construction leaders are working to develop a schedule to help teachers finalize moving […]

Read More April Recap

Brentwood Eagle Pride

Finishing touches are being installed throughout the Middle and High School renovation project to help make school a comfortable and fun place to learn. For instance, take the new vinyl graphic that was just installed in the gym to help show #BSDEaglePride for all students!

Read More Brentwood Eagle Pride

Gym Open House

The public is invited to see and experience the renovated gymnasium on Tuesday, February 4th! Brentwood High School will host a basketball tripleheader against Valley Park that evening. Admission to the games will be free and open to the public! This invitation will help the community see the progress being made on Prop B construction […]

Read More Gym Open House

Update – 1/13/2020

Construction is progressing throughout the building. Next month, we anticipate being able to move teachers and students into the new science rooms. Work is continuing on the Auditorium as well, including installation of accessibility ramps. Teachers are also participating in meetings to select new furniture. In order to help the community experience the new gymnasium, […]

Read More Update – 1/13/2020

Groundbreaking Ceremony – June 1st

On Saturday, June 1st, Brentwood School District will host a Groundbreaking Ceremony to mark the start of  middle and high school project construction funded by Proposition B. This short celebration will allow us to thank our community for their support and dedication to student success. Brentwood School District Groundbreaking CeremonySaturday, June 1st, 201910:00 – 10:30 […]

Read More Groundbreaking Ceremony – June 1st

UPDATE – 11/29/2018

We recently met with our architects and project manager and we are on schedule and on budget for the project. The team is continuing to refine costs to determine the exact scope of the work. We are confident that the budget will meet all of the priorities of the project, at this point we are […]

Read More UPDATE – 11/29/2018

UPDATE – 10/02/2018

Lots of exciting work happening on the project! I spent the day last Friday meeting with each of the departments at the high school as we gathered more input from the staff. Several great ideas surfaced during the day that will impact the final design. We received the initial report from the mechanical engineer and […]

Read More UPDATE – 10/02/2018