Update – 2/19/2021

A Building

  • Class is in session
  • Gym is open for classes
  • Cafeteria Fully Operational
  • Auditorium Construction complete.
    • BSD currently recoating floors under seating prior to opening space end of February.

B Building

  • Building Addition
    • Lobby and Offices – Early April
    • Main Addition – Early April
    • Exterior Curtainwall System Started 2/8/21
    • Interior walls framed and MEPFP roughing in all levels
    • Tape & Finish Drywall LL and L1
    • Multipurpose (Small Gym) – June
  • 1st Floor
    • Main Admin & Principal Offices – March
  • Lower Level
    • Lower Level Meeting Rooms to be turned over end of February

C Building

  • Turned over to the district
    • Students holding classes in the building
    • Restroom sinks replaced over Presidents’ Day Weekend

Elevators

  • #2 – B Building
    • Shaft Completed
    • Roofing completed
    • Electrical Rough-In Ongoing
    • Elevator company starting 1-2 weeks
    • Expected completion March
  • #3 – B/C Building
    • Excavation completed
    • Existing undocumented storm uncovered. Planned developed to repair Manhole in place and replace storm lines.
    • Expected completion End of June

Sitework

  • “A” Building
    • Sod weather completed
    • Sidewalk completed
    • Fencing removed
  • “B” Building
    • Site grading/utilities contactor expected completion late March – pending weather
  • “B” Courtyard
    • Exterior brick completed, continuing courtyard footings

Advertisement

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s