A Building
- Class is in session
- Gym is open for classes
- Cafeteria Fully Operational
- Auditorium Construction complete.
- BSD currently recoating floors under seating prior to opening space end of February.
B Building
- Building Addition
- Lobby and Offices – Early April
- Main Addition – Early April
- Exterior Curtainwall System Started 2/8/21
- Interior walls framed and MEPFP roughing in all levels
- Tape & Finish Drywall LL and L1
- Multipurpose (Small Gym) – June
- 1st Floor
- Main Admin & Principal Offices – March
- Lower Level
- Lower Level Meeting Rooms to be turned over end of February
C Building
- Turned over to the district
- Students holding classes in the building
- Restroom sinks replaced over Presidents’ Day Weekend
Elevators
- #2 – B Building
- Shaft Completed
- Roofing completed
- Electrical Rough-In Ongoing
- Elevator company starting 1-2 weeks
- Expected completion March
- #3 – B/C Building
- Excavation completed
- Existing undocumented storm uncovered. Planned developed to repair Manhole in place and replace storm lines.
- Expected completion End of June
Sitework
- “A” Building
- Sod weather completed
- Sidewalk completed
- Fencing removed
- “B” Building
- Site grading/utilities contactor expected completion late March – pending weather
- “B” Courtyard
- Exterior brick completed, continuing courtyard footings