Project Schedule Update
- Early Site Work is Complete
- Building Contractor Mobilized
- Site Survey and Staking
- Footings/Foundation Begin week of 9/20/21
Substantial Completion Estimate: Winter 2022
Outstanding Submittals & RFI’s
The following RFI’s are Outstanding:
- Roof Sheathing
- Storm Shelter Louvers
- Aluminum Feeders
Critical Submittals:
- Tilt Concrete Shops
- Plumbing Valves
- Domestic Water Piping Specialties
- Storm Drainage Piping Specialties
Owner Hot List / Risks
Schedule Risks
- Unforeseen Conditions
- Potential Material Delivery Delays
- Weather
- Potential Labor Shortage
Budget Risks
- Unforeseen Conditions
Contingency / Allowances
| Original Contingency: | $755, 200 |
| Contingency Spent: | $0 |
| Anticipated Changes: | $0 |
| Anticipated Contingency Remaining: | $755,200 |
| Unknown Conditions Allowance | |
| Original Allowance | $100,000 |
| Remaining Allowance | $100,000 |
McGrath/BECC Construction Contract
| Original Contract: | $15,104,000 |
| Changes to Date: | $0 |
| Current Contract: | $15,104,000 |




