At the May 18, 2021 Board of Education Meeting, Navigate Building Solutions presented the latest timeline information for the Middle and High School project. To view the entire presentation, view the meeting archive on the district YouTube channel at bit.ly/bsdyoutube.
B Building Update
- Lobby Addition (End of May Completion)
- Main Building Addition
- Level 2 (End of May)
- Level 1 (June)
- Lower Level (June)
- Multipurpose Room (August)
- Includes current temporary library space
- Lower Level (June)
- Conference/Meeting Rooms and Corridor Connector
Elevators
- #2 – B Building
- Elevator Company Complete
- Punch-list work ongoing
- Expected completion in June
- #3 – B/C Building
- Foundations are complete
- Waterproofing foundation walls
- CMU at shaft to start next week
- Expected completion at the end of July
Sitework
- B Building
- ADA Switchback ramp walls are complete – paving to take place next
- Circle drive south lane is cut to subgrade
- Sidewalks and stairs are being prepped and poured
- Parking pavers to begin in June
- Anticipated completion in July
- B Courtyard
- Complete