Elevators
- Elevator 2 (May 2021): Drywall returns framed an drywalled this week. Schindler electric to schedule inspection in the coming weeks.
- Elevator 3 (July 2021): Masonry infill window and waterproofing taking place this week. Backfill and retaining wall demo to happen next.
Building B Update
- Lobby Expansion (May 2021)
- Flooring installation underway.
- Aluminum storefront and doors in place
- MEPFP Trimming taking place.
- Lower Level Meeting/Staff Rooms (April 2021)
- Downspout install happening next Monday, May 10th.
- Level 1 Office/Admin Rooms (May 2021)
- MEPFP trimming taking place with storefront glass coming shortly after. Flooring is installed.
- Multipurpose
- Library pack up week of May 17th. School movers start during the week of May 24th.
- Demo to start no earlier than 5/27.
Building B Expansion Update
- Lower Level (June 2021)
- Ceramic tile installation started this week. Drywall taping and finish coat is ready for paint.
- Level 1 (June 2021)
- Started painting this week.
- Level 2 (May 2021)
- Aluminum window walls and glass this week.
- MEPFP Trim Out.
- Pop-Up (May 2021)
- Above Ceiling MEPFP.
Site Update (June 2021)
- Switch back ramp backfill this week.
- Site grading continuing.
- Sidewalks started south end.