Prop B Update – 5/7/2021

Elevators

  • Elevator 2 (May 2021): Drywall returns framed an drywalled this week. Schindler electric to schedule inspection in the coming weeks.
  • Elevator 3 (July 2021): Masonry infill window and waterproofing taking place this week. Backfill and retaining wall demo to happen next.

Building B Update

  • Lobby Expansion (May 2021)
    • Flooring installation underway.
    • Aluminum storefront and doors in place
    • MEPFP Trimming taking place.
  • Lower Level Meeting/Staff Rooms (April 2021)
    • Downspout install happening next Monday, May 10th.
  • Level 1 Office/Admin Rooms (May 2021)
    • MEPFP trimming taking place with storefront glass coming shortly after. Flooring is installed.
  • Multipurpose
    • Library pack up week of May 17th. School movers start during the week of May 24th.
    • Demo to start no earlier than 5/27.

Building B Expansion Update

  • Lower Level (June 2021)
    • Ceramic tile installation started this week. Drywall taping and finish coat is ready for paint.
  • Level 1 (June 2021)
    • Started painting this week.
  • Level 2 (May 2021)
    • Aluminum window walls and glass this week.
    • MEPFP Trim Out.
  • Pop-Up (May 2021)
    • Above Ceiling MEPFP.

Site Update (June 2021)

  • Switch back ramp backfill this week.
  • Site grading continuing.
  • Sidewalks started south end.
Building B Expansion underway
Advertisement

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s