During the August 18, 2020 Board of Education meeting, the president of K&S Construction provided a schedule update for the remainder of the Middle/High School construction project. You can view the entire Board Meeting on our YouTube channel at bit.ly/bsdyoutube.
Below is a copy of the revised schedule. A PDF of the schedule is available by clicking here.
First Floor

Large Gymnasium – Complete
1st Floor Building C Classrooms – Complete
- Language Arts
- Flexible Learning Spaces
- Testing Labs
Cafeteria – Complete
Auditorium – 11/15/2020
1st Floor Classrooms – 8/21/2020
- Art
- Math
- Language Arts
- Social Studies
New Commons and Entrance – 12/07/2020
Middle School Offices – 10/02/2020
Elevators – 11/27/2020
Access Ramp – 8/28/2020
1st Floor Storage and Staff Areas – 10/02/2020
- Student Council Storage
- Meeting Rooms
- Mechanical Closets
Second Floor

Large Gymnasium – Complete
2nd Floor Building C Classrooms – Complete
- Math
- Social Studies
- Lecture Hall
2nd Floor Classrooms – 08/21/2020
- Math
- Language Arts
- Science
Staff Offices and Classrooms – 10/02/2020
- Nurse’s Office
- Staff Lounge
- Reading
FACS and SSD Rooms – 10/02/2020
High School Offices – 11/16/2020
Small Gymnasium – 01/07/2021
Third Floor

3rd Floor Science Labs – Completed
- Biology
- Chemistry
- Physics
- Science Flex Lab
3rd Floor Classrooms – 10/02/2020
- World Languages
- Art
- Math
- Language Arts
- Social Studies
- Flexible Learning Space