Prop B Update – 4/16/2021

Elevators Elevator 2 (April 2021) Schindler to complete work today. Charter line is complete. Punch work will take place for 1-2 weeks followed by Final State Inspection. Elevator 3 (July 2021)  Foundation pours taking place this week with slab pours next week. Building B Update Lobby Expansion (May 2021) Drywall taping ongoing currently. Painting taking […]

Advertisement

Read More Prop B Update – 4/16/2021

Prop B Update – 4/2/2021

Over Spring Break, construction crews worked on areas of the building normally occupied by students and staff, primarily tackling warranty and punch-list work such as tackboards, LVT flooring, and painting. Elevator 2 (April 2021) Schindler started this week. Charter line install is taking place today. On schedule for mid-late April for completion. Elevator 3 (July […]

Read More Prop B Update – 4/2/2021

Prop B Update – 3/12/2021

Elevator Updates Elevator 2 – Disconnect switch installation began this week. Schindler (elevator contractor) was on site for a pre-install walk this week. Schindler expects a start date of 3/31, with final completion still looking like the end of April. Elevator 3 – Foundation underpinning completed 3/2/21. Direction was given to encase 8” storm drain […]

Read More Prop B Update – 3/12/2021

Prop E (Phase II) Upcoming Events

Be sure to check out the last post to read the latest update and watch the latest video about Prop E (Phase II) facilities and upcoming events. Next week, early childhood and elementary families and staff will have the opportunity to attend a Virtual Open House for their home school about the Phase II process […]

Read More Prop E (Phase II) Upcoming Events

Prop E Timeline

Timeline Overview Phase 1: McGrath/BECC Early Sitework Package Bidding: April/May 2021 Project Bidding: May/June 2021 Construction Completed: December 2022 Fall 2023 – McGrath students attend school in new building; Mark Twain students begin their year at the old McGrath building Phase 2: Mark Twain Elementary Design Hold: June-September 2021 Concept Design: October-December 2021 Complete Design: March […]

Read More Prop E Timeline

Update – 2/26/21

Elevator 2 – The lobby roof was installed this week with metal flashings and gutters coming next. Disconnect switch ship date still 3/3/21. Targeting completion in April. Elevator 3 – Proceeding with foundation underpinning with expected completion by the end of this week. Next week will see the start of foundations for the elevator pit. Building B Update: In the new lobby expansion, windows have been going […]

Read More Update – 2/26/21

Update – 2/19/2021

A Building Class is in session Gym is open for classes Cafeteria Fully Operational Auditorium Construction complete. BSD currently recoating floors under seating prior to opening space end of February. B Building Building Addition Lobby and Offices – Early April Main Addition – Early April Exterior Curtainwall System Started 2/8/21 Interior walls framed and MEPFP […]

Read More Update – 2/19/2021

Update – 2/8/2021

Elevator 2 – We are still tracking electrical switch ship date of 2/10/21. Completion is expected mid-March Elevator 3 – A recently discovered manhole and storm line are creating conflicts with Elevator 3, preventing foundation work from continuing. The manhole and storm line were covered by asphalt and did not appear on any drawings. The […]

Read More Update – 2/8/2021

Update – 1/20/2021

A Building Class is in session Gym is open for classes Auditorium complete. Ittner to perform Punchlist this week. “Pop Up” area roof completed. Existing RTU remained in place Structural steel completed Finishes will be with the B addition B BUILDING Building Addition Lobby and Offices – March 31 Corridor turned over to BSD January […]

Read More Update – 1/20/2021