Prop B Update – 6/17/2021
Elevators Elevator 2 (June 2021) – Floor transitions, paint front, schedule Schindler for final inspection TBD. Elevator 3 (July/August 2021) – Masonry work started this week. Building B Update Lobby Expansion and Admin Offices (June 2021) Punch week happening this week Color Art End of June Lower Level Meeting/Staff Rooms (April 2021) Color Art furniture […]
Read More Prop B Update – 6/17/2021