Prop B Update – 6/17/2021

Elevators Elevator 2 (June 2021) – Floor transitions, paint front, schedule Schindler for final inspection TBD. Elevator 3 (July/August 2021)  – Masonry work started this week. Building B Update Lobby Expansion and Admin Offices (June 2021) Punch week happening this week Color Art End of June Lower Level Meeting/Staff Rooms (April 2021) Color Art furniture […]

Read More Prop B Update – 6/17/2021

Prop B Update – 6/10/2021

ELEVATORS Elevator 2 (June 2021) Floor transitions, paint front, schedule Schindler for final inspection TBD. Elevator 3 (July/August 2021)  Masonry work started this week. Building B Update Lobby Expansion and Admin Offices (June 2021) Punch week of 6/14/21 Lower Level Meeting/Staff Rooms (April 2021) Furniture next couple weeks Multipurpose (August 2021) Painting this week. Building […]

Read More Prop B Update – 6/10/2021

Prop E Renderings

Since the passing of Proposition E in June 2020, the district and its Elementary Facilities Design Committee has worked with stakeholders throughout the community to design and plan a McGrath/BECC campus that will serve the needs of students, families, staff, and the community for generations to come. The following images are conceptual renderings that give […]

Read More Prop E Renderings

Prop B Timeline (Summer 2021)

With a majority of the project completed, the final areas of the Middle/High School construction project are scheduled to be finalized during Summer 2021. The areas listed below are what remains of the project to be completed. Anything not listed here has been turned over to the district and is in use or in the […]

Read More Prop B Timeline (Summer 2021)

Prop E Logistics Planning

Early sitework is scheduled to begin at the McGrath campus at the end of May. As the community will begin seeing work start to take place in the neighborhood for the new BECC/McGrath construction, please review the following materials that will help explain the site logistics and planning. Prop E (Elementary & Early childhood) Timeline […]

Read More Prop E Logistics Planning

Prop B Update – 5/19/2021

At the May 18, 2021 Board of Education Meeting, Navigate Building Solutions presented the latest timeline information for the Middle and High School project. To view the entire presentation, view the meeting archive on the district YouTube channel at bit.ly/bsdyoutube. B Building Update Lobby Addition (End of May Completion) Main Building Addition Level 2 (End […]

Read More Prop B Update – 5/19/2021

Prop B Update – 5/7/2021

Elevators Elevator 2 (May 2021): Drywall returns framed an drywalled this week. Schindler electric to schedule inspection in the coming weeks. Elevator 3 (July 2021): Masonry infill window and waterproofing taking place this week. Backfill and retaining wall demo to happen next. Building B Update Lobby Expansion (May 2021) Flooring installation underway. Aluminum storefront and […]

Read More Prop B Update – 5/7/2021

Prop B Update – 4/30/2021

Elevators Elevator 2 (May 2021) JDS to complete masonry returns today, drywall complete with MEPFP next week. Elevator 3 (July 2021)  Masonry today, waterproofing next week and demo of retaining wall and backfill to follow. Building B Update Lobby Expansion (May 2021) MEPFP Trim started this week. Lower Level Meeting/Staff Rooms (April 2021) Downspout and […]

Read More Prop B Update – 4/30/2021

Prop B Update – 4/23/2021

Elevators Elevator 2 (May 2021) Schindler installation is complete. Punch/completion items by K&S to take 1-2 weeks, then Schindler will return to make final electrical connection and inspections. Elevator 3 (July 2021) Foundations are complete. Waterproofing walls this week, backfill and masonry to be next week. Building B Update Lobby Expansion (May 2021) Painting started […]

Read More Prop B Update – 4/23/2021

Prop E – Upcoming Dates

Over the past several weeks, the Brentwood community has had opportunities to participate in events and provide feedback about the Elementary/Early Childhood facilities process. Here are some upcoming dates with opportunities to learn more: April 29, 2021 – Design Committee Meeting May 18, 2021 – Board of Education Presentation To review background information, presentations, an FAQ, […]

Read More Prop E – Upcoming Dates