Prop B Update – 4/16/2021

Elevators

  • Elevator 2 (April 2021)
    • Schindler to complete work today. Charter line is complete. Punch work will take place for 1-2 weeks followed by Final State Inspection.
  • Elevator 3 (July 2021) 
    • Foundation pours taking place this week with slab pours next week.

Building B Update

  • Lobby Expansion (May 2021)
    • Drywall taping ongoing currently.
    • Painting taking place next week.
  • Lower Level Meeting/Staff Rooms (April 2021)
    • Downspout work taking place first followed by floor leveling.
  • Level 1 Office/Admin Rooms (May 2021)
    • LVT2 material for Admin area has been delayed to late April, pushing this space’s timeline into May.
  • Multipurpose
    • Temporary library pack-up to take place the week of May 17th with goal to be moved out by 5/24.
    • Demolition of temporary library space to start the week following the 17th.

Building B Expansion Update

  • Courtyard commemorative pavers completed this week. Power washing of the North Wall taking place.
  • Lower Level (June 2021)
    • French drain work wrapping up. Electric and plumbing connections next week. K&S can then complete finishes. 
  • Level1 (June 2021)
    • Drywall taping and MEPFP underway.
  • Level 2 (May 2021)
    • Painting to start next week.
  • Pop-Up (May 2021)
    • Painting next week and then ceiling install.

Site Update (June 2021)

  • Retaining wall for the ramp at the south side of circle drive had footings poured this week.
  • Excavation for south stairs outside of expansion entry is underway.
Advertisement

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s