Prop B Update – 3/12/2021

Elevator Updates

Elevator 2 – Disconnect switch installation began this week. Schindler (elevator contractor) was on site for a pre-install walk this week. Schindler expects a start date of 3/31, with final completion still looking like the end of April.

Elevator 3 – Foundation underpinning completed 3/2/21. Direction was given to encase 8” storm drain to keep things moving forward. Carlyle waterproofing rep was out and new PR issued this week for pricing.

Building B Update

  • Lobby Expansion – Window & Storefront Installation underway.
  • Lower Level Meeting/Staff Rooms – Floor leveling is proceeding on schedule. Mailbox modifications complete.
  • Level 1 Office/Admin Rooms – 
    • LVT2 Material delivery for Admin area end of March.
    • Connector to Expansion ramp work being scheduled for after hours.

Building B Expansion Update

  • Lower Level Water Infiltration – Foundation drain lines flushed this week by K&S. Rain will help determine severity. Pricing has been submitted by K&S. In review with Ittner/Navigate/BSD. 
  • Level 1 – continuing with drywall and MEPFP.
  • Level 2 – continuing framing and MEPFP rough-in.
  • Exterior glass window system and metal panel & copings installation. Courtyard planter.

Weightroom

  • Pending direction on water infiltration remediation.

Site Update

  • Fire FDC and underground completed this week. Underground utilities working south to north, started this week.
  • Retaining wall work will follow behind underground utilities work.
Advertisement

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s