BMS/BHS Photo Tour

Check out the slides below to get a sense of all the new and updated areas of Brentwood Middle and High School! Thank you to our community for supporting these much-needed upgrades to our facilities. Not only does this modernize our secondary schools, it helps future-proof our spaces. By offering lots of flexible learning areas, […]

Advertisement

Read More BMS/BHS Photo Tour

McGrath Sitework Update

This summer, crews have been hard at work preparing the McGrath site for the new McGrath/BECC building. While it may not have looked very exciting so far, things are about to get a lot more interesting! From the outside, you’ve mostly seen what just looks like dirt being moved around. But if you take a […]

Read More McGrath Sitework Update

Prop B Update – 8/20/2021

While work will continue in limited areas of the building for another month or so as work on the final elevator continues, all class and student areas of the building, including the new offices, are open and ready for the start of the school year. Please pay attention to new signage near the front of […]

Read More Prop B Update – 8/20/2021

August 31st Community Update

On August 31st, we will host a Facilities and Construction Update for our community. The event will be livestreamed to our YouTube channel at bit.ly/bsdyoutube at 6:00 PM. Representatives from the architect team (HTK), the owner’s representative (Navigate), and the district will be on hand to provide updates and answer questions. We hope you will […]

Read More August 31st Community Update

Prop B Update – 7/29/2021

Elevators Elevator 2 (August 2021): K&S addressing all issues from failed inspection to be complete this week, re-inspection next week. Elevator 3 (September 2021): Camera/Jet of the 8” completed. Elevator Lobbies demo taking place in Bldg C. Steel roof decking being installed with roofing to follow next week. Schindler electrical following roof dry in. Building […]

Read More Prop B Update – 7/29/2021

ICS Named McGrath Contractor

During the July 20th, 2021 Board of Education meeting, the Brentwood School Board unanimously approved ICS as the construction contractor for the new McGrath building. ICS was recommended after a thorough vetting and interview process conducted by District personnel, Board Members, and the school district’s owner’s representative, Navigate Building Solutions. “ICS has shown a commitment […]

Read More ICS Named McGrath Contractor

Prop B Update – 7/8/2021

Elevators Elevator 2 (June 2021) Schindler is on site to complete their scope this week. Final inspection scheduled for next week, day/time TBD. Elevator 3 (July/August 2021)  Utility contractor to start today with area drains. Camera/Jet of the 8” to be scheduled next week. Grading contractor bringing area to rough grade. Building B Update Lobby […]

Read More Prop B Update – 7/8/2021

Prop B Update – 7/1/2021

Elevators Elevator 2 (June 2021) – Schindler to be scheduled for final connection and inspection. K&S to advise. Elevator 3 (July/August 2021)  – Masonry work completed. – Grading contractor bringing area to rough grade. Building B Update Lobby Expansion and Admin Offices (June 2021) Color Art working on options for Principals office furniture Friday 7/2/21.  […]

Read More Prop B Update – 7/1/2021