Prop B Update – 4/23/2021

Elevators

  • Elevator 2 (May 2021)
    • Schindler installation is complete. Punch/completion items by K&S to take 1-2 weeks, then Schindler will return to make final electrical connection and inspections.
  • Elevator 3 (July 2021)
    • Foundations are complete. Waterproofing walls this week, backfill and masonry to be next week.

Building B Update

  • Lobby Expansion (May 2021)
    • Painting started this week and will continue into next week.
  • Lower Level Meeting/Staff Rooms (April 2021)
    • Downspout work finishing up, which will be followed by floor leveling.
  • Level 1 Office/Admin Rooms (May 2021)
    • Painting wrapped up this week.
    • Storefront glass installation next week.
    • LVT2 Material for Admin area was delayed now until late April, pushing this space into May.
  • Multipurpose
    • Temporary library pack up week of May 17th with the goal to be moved out by 5/24 in order to start renovations of the temporary library space beginning on 5/27.

Building B Expansion Update

  • Courtyard One opening to be completed with brick work next week and then power washing.
  • Lower Level (June 2021)
    • French drain work is wrapping up. Electric and plumbing connections will be fitted next week. Afterward, K&S can complete finishes.
  • Level 1 (June 2021)
    • Drywall taping and MEPFP taking place now.
  • Level 2 (May 2021)
    • Painting to start next week.
  • Pop-Up (May 2021)
    • Painting to start next week, followed by ceiling installation.

Site Update (June 2021)

  • Retaining wall for the ramp at south side of circle drive had its footings poured this week.
  • Excavating for south stairs outside of expansion entry is underway.
Advertisement

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s