Elevators
- Elevator 2 (May 2021)
- Schindler installation is complete. Punch/completion items by K&S to take 1-2 weeks, then Schindler will return to make final electrical connection and inspections.
- Elevator 3 (July 2021)
- Foundations are complete. Waterproofing walls this week, backfill and masonry to be next week.
Building B Update
- Lobby Expansion (May 2021)
- Painting started this week and will continue into next week.
- Lower Level Meeting/Staff Rooms (April 2021)
- Downspout work finishing up, which will be followed by floor leveling.
- Level 1 Office/Admin Rooms (May 2021)
- Painting wrapped up this week.
- Storefront glass installation next week.
- LVT2 Material for Admin area was delayed now until late April, pushing this space into May.
- Multipurpose
- Temporary library pack up week of May 17th with the goal to be moved out by 5/24 in order to start renovations of the temporary library space beginning on 5/27.
Building B Expansion Update
- Courtyard One opening to be completed with brick work next week and then power washing.
- Lower Level (June 2021)
- French drain work is wrapping up. Electric and plumbing connections will be fitted next week. Afterward, K&S can complete finishes.
- Level 1 (June 2021)
- Drywall taping and MEPFP taking place now.
- Level 2 (May 2021)
- Painting to start next week.
- Pop-Up (May 2021)
- Painting to start next week, followed by ceiling installation.
Site Update (June 2021)
- Retaining wall for the ramp at south side of circle drive had its footings poured this week.
- Excavating for south stairs outside of expansion entry is underway.