ELEVATORS
- Elevator 2 (June 2021)
- Floor transitions, paint front, schedule Schindler for final inspection TBD.
- Elevator 3 (July/August 2021)
- Masonry work started this week.
Building B Update
- Lobby Expansion and Admin Offices (June 2021)
- Punch week of 6/14/21
- Lower Level Meeting/Staff Rooms (April 2021)
- Furniture next couple weeks
- Multipurpose (August 2021)
- Painting this week.
Building B Expansion Update
- Lower Level (June 2021)
- Floor prep this week, flooring next week is tentative.
- Level 1 (June 2021)
- MEPFP Trim Out.
- Column Wraps.
- Flooring next.
- Level 2 (June 2021)
- Punched 6/11
- Furniture Move-In 6/14
Site Update (July/August 2021)
- South Paver Area start pavers next week.
- Pouring sidewalks and curbs throughout.
- Water/Gas Line discovered 6/7 at NW side impacting west paver section.