Prop B Update – 6/10/2021

ELEVATORS

  • Elevator 2 (June 2021)
    • Floor transitions, paint front, schedule Schindler for final inspection TBD.
  • Elevator 3 (July/August 2021) 
    • Masonry work started this week.

Building B Update

  • Lobby Expansion and Admin Offices (June 2021)
    • Punch week of 6/14/21
  • Lower Level Meeting/Staff Rooms (April 2021)
    • Furniture next couple weeks
  • Multipurpose (August 2021)
    • Painting this week.

Building B Expansion Update

  • Lower Level (June 2021)
    • Floor prep this week, flooring next week is tentative.
  • Level 1 (June 2021)
    • MEPFP Trim Out.
    • Column Wraps.
    • Flooring next.
  • Level 2 (June 2021)
    • Punched 6/11
    • Furniture Move-In 6/14

Site Update (July/August 2021)

  • South Paver Area start pavers next week.
  • Pouring sidewalks and curbs throughout.
  • Water/Gas Line discovered 6/7 at NW side impacting west paver section.
Advertisement

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s