Project Timeline Update

A Building

  • Class is in session
  • Gym is open for classes
  • Auditorium stage curtains installing this week. Turnover to BSD over the holiday break.
  • “Pop Up” area mason finished walls. Structural steel set. Roofing expected 12/21.
  • Remaining punch list items expected to be completed over the holiday break.
“Pop-Up” Area
Auditorium with new curtains, carpeting, and seats

B BUILDING

  • Building Addition
    • Lobby and Offices – March 3
      • Corridor turned over to BSD January 11
      • Concrete SOG poured
      • Roofing starting December 18th
    • Main Addition – March 1st
    • Concrete SOG are poured
    • Roofing starting December 21
  • 3rd Floor – Turned over
  • 2nd floor – Turned over
  • 1st Floor
    • Rooms at bottom of main stairs – January 8
    • Structural steel at chimney completed

C BUILDING

  • Turned over to the district
  • Students holding classes in the building
  • Remaining punch list items to be completed over the holiday break

Elevators

  • #2 – B Building
    • Shaft Completed
    • Roofing starting December 16
    • Door openings being demoed this week at night
    • Elevator company starting 12/22
    • Expected completion Feb 1
  • #3 – B/C Building
    • Excavation on going
    • Slow process due to underpinning required
    • Expected completion April 1

Sitework

  • “A” Building
    • Sod weather pending December 16th
    • Sidewalk infill December 17th
  • “B” Building
    • Site grading/utilities contactor December 21st
    • ADA ramp demolition over the holiday break
    • Elevator 3 excavation ongoing

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s