Prop B Update – 6/10/2021

ELEVATORS Elevator 2 (June 2021) Floor transitions, paint front, schedule Schindler for final inspection TBD. Elevator 3 (July/August 2021)  Masonry work started this week. Building B Update Lobby Expansion and Admin Offices (June 2021) Punch week of 6/14/21 Lower Level Meeting/Staff Rooms (April 2021) Furniture next couple weeks Multipurpose (August 2021) Painting this week. Building […]

Read More Prop B Update – 6/10/2021

Prop B Timeline (Summer 2021)

With a majority of the project completed, the final areas of the Middle/High School construction project are scheduled to be finalized during Summer 2021. The areas listed below are what remains of the project to be completed. Anything not listed here has been turned over to the district and is in use or in the […]

Read More Prop B Timeline (Summer 2021)

Prop B Update – 5/19/2021

At the May 18, 2021 Board of Education Meeting, Navigate Building Solutions presented the latest timeline information for the Middle and High School project. To view the entire presentation, view the meeting archive on the district YouTube channel at bit.ly/bsdyoutube. B Building Update Lobby Addition (End of May Completion) Main Building Addition Level 2 (End […]

Read More Prop B Update – 5/19/2021

Prop B Update – 5/7/2021

Elevators Elevator 2 (May 2021): Drywall returns framed an drywalled this week. Schindler electric to schedule inspection in the coming weeks. Elevator 3 (July 2021): Masonry infill window and waterproofing taking place this week. Backfill and retaining wall demo to happen next. Building B Update Lobby Expansion (May 2021) Flooring installation underway. Aluminum storefront and […]

Read More Prop B Update – 5/7/2021

Prop B Update – 4/30/2021

Elevators Elevator 2 (May 2021) JDS to complete masonry returns today, drywall complete with MEPFP next week. Elevator 3 (July 2021)  Masonry today, waterproofing next week and demo of retaining wall and backfill to follow. Building B Update Lobby Expansion (May 2021) MEPFP Trim started this week. Lower Level Meeting/Staff Rooms (April 2021) Downspout and […]

Read More Prop B Update – 4/30/2021

Prop B Update – 4/23/2021

Elevators Elevator 2 (May 2021) Schindler installation is complete. Punch/completion items by K&S to take 1-2 weeks, then Schindler will return to make final electrical connection and inspections. Elevator 3 (July 2021) Foundations are complete. Waterproofing walls this week, backfill and masonry to be next week. Building B Update Lobby Expansion (May 2021) Painting started […]

Read More Prop B Update – 4/23/2021

Prop B Update – 4/16/2021

Elevators Elevator 2 (April 2021) Schindler to complete work today. Charter line is complete. Punch work will take place for 1-2 weeks followed by Final State Inspection. Elevator 3 (July 2021)  Foundation pours taking place this week with slab pours next week. Building B Update Lobby Expansion (May 2021) Drywall taping ongoing currently. Painting taking […]

Read More Prop B Update – 4/16/2021

See the New Gym!

This week, the large gym was fully opened to students! While there are still a few finishing touches with graphics and details around the entrance, the new large gym facility is beautiful and being used by students in PE and athletics. In addition, the new locker room areas are ready along with some of the […]

Read More See the New Gym!

UPDATE – PROJECT TIMELINE

As we are getting closer to the start of the middle school/high school project I thought it would be helpful to post the timeline for the project. February 2019- Project put out for bid March 2019– Construction companies interviewed and bid awarded April 2019– Begin staging the site and breaking ground Summer of 2019– Major […]

Read More UPDATE – PROJECT TIMELINE