Update – 10/20/2020

Significant progress has been made in Building B. As floors in rooms are completed, custodial/maintenance crews are cleaning and moving furniture.

Furniture is almost finished in all of the classrooms with adjustments being made by teachers and district staff over the coming days.

Wireless access points and new phones are being installed throughout the building.

As the building transitions to welcome students back to in-person learning, please be aware of the following precautions taken by the construction teams:

  • Masks required for construction crew
  • Partitions to separate any construction crew from students/staff
  • Handwashing/hand sanitizing stations
  • Additional health and safety checks and protocols
Refinished hardwood floors in world language classrooms.
Advertisement

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s