Update – 5/22/2020

Construction work is continuing well as we head into the summer months. Here’s a snapshot of upcoming work happening throughout the construction process:

  • Building A abatement is complete. Demolition and reconstruction of the rooms has begun in that area of the school.
  • Building B masonry work is continuing as planned. New steel has been delivered for roof/upper level and brick work has started in west side of building.
  • High school heat pump installation continues including control wiring and reconstruction has started in the FACS room and suite.
  • Building C framing is completed and drywall work is nearing completion. Conducting additional flooring tests in that area for adhering new carpet.
  • Temporary weight room has been moved and is now abated so work can continue there.

For the latest news and information, please follow the district on Facebook, Twitter, and Instagram @BrentwoodMOSD.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s