UPDATE – PROJECT TIMELINE

As we are getting closer to the start of the middle school/high school project I thought it would be helpful to post the timeline for the project.

February 2019- Project put out for bid

March 2019– Construction companies interviewed and bid awarded

April 2019– Begin staging the site and breaking ground

Summer of 2019– Major construction occurring including the new construction of the commons and library

2019-2020 School Year– Temporary classrooms created in spaces such as the existing library and lecture hall allowing small blocks of 3-4 adjacent classrooms to be renovated at a time.

Summer of 2020– Final push and project to be completed by the start of Fall 2020

Prop B Construction Timeline
Advertisement

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s